Scope of Work:
Installed multiple 40,000-lb process units on second-level platform. Involved offloading, inplant transport, and precise placement.
Key Challenges & Solutions:
- Staging & Access: With a high volume of units arriving at varying times, strategic staging was critical. PSC collaborated with the client to establish a zoned/quadrant layout, ensuring efficient sequencing and access throughout the installation phase.
- Precision Lifting Requirements: All lifts were required to maintain ±6” level tolerance using all designated lifting lugs. PSC engineered and implemented a custom 3-beam modular spreader bar configuration to meet these lift criteria.
- Limited Undercarriage Access: Due to geometry and plant layout constraints, traditional rigging methods were not feasible. PSC and the client developed a custom transport frame, allowing the integration of two 3’ axles and a Traksporter mounting bracket, enabling precise navigation through the facility.
Equipment Utilized:
- Liebherr LTM 1130 All-Terrain Crane
- Tadano GR-1200XL Rough Terrain Crane
- Traksporter System
- Modular Spreader Beams