Project Overview:
PSC Crane and Rigging was contracted by the Alabama State Docks for the heavy transport and staging of a Krupp Stacker/Reclaimer originally located in Ashtabula, Ohio. The project involved complete logistical planning, heavy transport engineering, and execution for relocating this oversized industrial equipment to Mobile, Alabama. The relocation was time-sensitive due to seasonal constraints affecting the St. Lawrence Seaway.
Scope of Work:
Full transport of stacker/reclaimer from Ashtabula, OH to Mobile, AL. Involved staging, loading onto a barge, marine transport, offloading, and final storage.
Key Challenges & Solutions:
Seasonal Freezing Risk: Fast-track scheduling and coordination with marine transport.
Equipment Utilized:
- Goldhofer PST SL-E
- 12-Line SPMTs
- Custom rigging stands, deck mats, plating