Minteq System Reinforcement

Scope of Work:

Installation of steel reinforcement for new Minteq system. Includes removing and reinstalling ten (10) 1-1/4” x 4’x8’ plates, rigging and welding large steel members.

Key Challenges & Solutions:

  • Short outage window: Dual shifts to maximize output.
  • Heavy components: Overhead crane and skilled rigging.
  • Efficient weld prep: Arc gouging for quick and clean removal.

Equipment Utilized:

  • Overhead Crane
  • Arc Gouging Tools
  • MIG Welding Equipment
     